A Notice of Commencement tells everyone who works on your project who owns the property, who the contractor is, and where notices should go. In Florida, it's the owner's job. Section 713.13(1)(a) says the owner or the owner's authorized agent, "before actually commencing to improve any real property," shall record a notice of commencement in the clerk's office and post a certified copy, or a notarized statement that it was filed with a copy attached, at the site.

Every building permit card in Florida carries this warning in bold capitals: "YOUR FAILURE TO RECORD A NOTICE OF COMMENCEMENT MAY RESULT IN YOUR PAYING TWICE FOR IMPROVEMENTS TO YOUR PROPERTY" (s. 713.135(1)(a)).

When you need one

  • Most permitted projects over $2,500. Improvements exempt under s. 713.02(5), meaning direct contracts of $2,500 or less, don't need one (s. 713.13(1)(a)).
  • Restarting after default or abandonment. The same duty applies when you recommence an improvement (s. 713.13(1)(a)).
  • Changing contractors. An amendment can't swap contractors. You need a new notice of commencement or a notice of recommencement (s. 713.13(5)(a)).

The permit office's role

The building department must give you blank forms and a DBPR summary of the lien law when you apply for a permit (s. 713.135(1)(b) and (d)). It may not require a recorded notice to apply for or get the permit (s. 713.135(1)(f)). But when the direct contract is greater than $5,000, you must file a copy with the permit office before the first inspection, and no later inspection will be performed or approved until you do (s. 713.135(1)(e)).

The permit-office rules in s. 713.135(1) don't apply to a direct contract under $15,000 to repair or replace an existing heating or air-conditioning system (s. 713.135(1)(f)).

What goes in it

The statutory form in s. 713.13(1)(d) asks for:

  1. The legal description and street address of the property (and tax folio number if available)
  2. A general description of the improvement
  3. Owner name and address, interest in the property, and fee simple titleholder if different
  4. Contractor name, address and phone
  5. Surety and bond amount, if there's a payment bond (attach a copy of the bond)
  6. Lender name, address and phone
  7. A Florida person designated to receive notices for you, if you choose one
  8. Anyone else you want to receive copies of lienors' notices
  9. The expiration date

The owner signs before a notary, in person or by online notarization. The owner "must sign the notice of commencement and no one else may be permitted to sign in his or her stead" (s. 713.13(1)(g)).

Deadlines that matter

Rule What it means for you Statute
Record and post before the first inspection Have it on the site before the inspector arrives s. 713.13(1)(d)
Void if work doesn't start in 90 days Don't record too early s. 713.13(2)
Expires 1 year after recording unless it states otherwise Contracts longer than a year must state a longer period s. 713.13(1)(c)-(d)
Payments after expiration are improper You may have to pay twice s. 713.13(1)(c)
Amend within the effective period You can extend it or fix errors s. 713.13(5)

When you record an amendment, you must serve a copy on the contractor and on each lienor who serves notice before or within 30 days after it's recorded (s. 713.13(5)(b)).

Why it protects you

The notice gives constructive notice that liens may be recorded and sets their priority, but recording it "does not constitute a lien, cloud, or encumbrance" on your property (s. 713.13(3)). It also tells subs and suppliers where to send the Notice to Owner, which is how you learn who you need lien releases from. Without a recorded notice, a lienor may rely on the information in the building permit application instead (s. 713.06(2)(e)).

The full sequence, from Notice to Owner to final payment affidavit, is in Florida construction lien law.

If you have a loan

A lender must record the notice of commencement before disbursing any construction funds to the contractor. The lender doesn't have to post it; that stays with you (s. 713.13(7)). The statutory warning tells owners who intend to obtain financing to consult the lender or an attorney before recording.

Related pages

Sources

Frequently Asked Questions

Who files the Notice of Commencement in Florida?

The owner or the owner's authorized agent records it in the clerk's office, and the owner must sign it personally; no one else may sign in the owner's stead (s. 713.13(1)(a) and (1)(g), F.S.). If you have a construction loan, the lender must record it before disbursing construction funds to the contractor, but posting it at the site stays your job (s. 713.13(7)).

Do I need a Notice of Commencement for a small job in Florida?

Not for an improvement exempt under s. 713.02(5), which covers direct contracts of $2,500 or less (s. 713.13(1)(a), F.S.). Separately, the permit office must require a copy before the first inspection only when the direct contract is greater than $5,000 (s. 713.135(1)(e)).

How long is a Florida Notice of Commencement good for?

It's void if the improvement isn't actually started within 90 days after recording (s. 713.13(2), F.S.). The expiration date is one year after recording unless the notice specifies a different date (s. 713.13(1)(d)), and it must state a longer period if the contract runs more than a year (s. 713.13(1)(c)).

What happens if I pay my contractor after the Notice of Commencement expires?

The statute's warning says payments made after expiration are considered improper payments under s. 713.13 and 'can result in your paying twice for improvements to your property' (s. 713.13(1)(c)-(d), F.S.). You can amend a notice within its effective period to extend it (s. 713.13(5)).